Activate FTE / headcount needs correlation (manual assessment method)
To enable the FTE / Headcount option when the needs assessment method is manual, go to Project Settings > Global Settings.
In the Workforce needs section, check the Correlate FTE needs with headcount needs option.
Once checked, new options for correlation appear on the right:
Choose the mode that should "govern" the other
Choose how to calculate the workforce needs for the "governed" mode
Maintain the current headcount/FTE ratio over time. Example: If 10 headcount correspond to 5 FTE today, then in the future 20 headcount will correspond to 10 FTE.
Application of the same +/- variation in both modes. Example: 10 employees correspond to 5 FTE today. If in the future I need 12 headcount (10+2), then I will need 7 FTE (5+2).
Click on Save.